New TEXAS Subcontractor notices effective January 1, 2022

By January 6, 2022No Comments

The state of TEXAS enacted new lien law changes effective January 1, 2022 that simplifies the 1st notice process for subcontractors. Notices that no longer have legal relevance include:
-Specially Fabricated Materials notice
-Second Month notice
-Notice of Contractual Retainage

Now, subcontractors simply need to send one of two notices by the 15th day of the third month when there is a balance due:
-TEXAS Notice Of Claim For Unpaid Labor Or Materials
-TEXAS Notice Of Claim For Unpaid Retainage

New 2022 TEXAS 1st notice menu

PreLien2Lien online and the desktop Lien Service edition have both been updated to reflect the law changes.