Home » 2020 » May (Page 2)

Recording a CO Statement of Lien in El Paso County

An Englewood, CO subcontractor that specializes in asbestos and lead-based paint abatement asked our TRADITION LIEN SERVICE division to record a COLORADO Statement of Lien (Colorado Revised Statutes § 38-22-109(1)) on a small shopping center located in Colorado Springs, CO within El Paso County. According to Wikipedia, the Census Bureau’s 2018 estimate indicates that El Paso County is the second-most populous county in Colorado, after the City and County of Denver.

COLORADO Revised Statutes § 38-22-109 mandates that General/Prime contractors and Subcontractors on private Commercial projects can record a notarized COLORADO Statement Of Lien up to four (4) months after the last day providing equipment, labor, materials or services if the Owner was previously given a COLORADO Notice Of Intent To File A Lien Statement and pre-recorded COLORADO Statement Of Lien ten (10) days prior to recording the lien. Record at the Clerk and Recorder’s Office in the county where the project is located. Cost to record a lien with the El Paso County Clerk is $13 for first page and $5 for each additional page. The office does accept out of state business checks. Make the check out to EL PASO COUNTY CLERK & RECORDER. Include a self addressed stamped envelope.

Turn around time to record is 1-2 business days. Recorded liens and releases will be returned within 2-5 business days.

Once a COLORADO Statement of Lien is recorded, as Claimant you are required to initiate a lawsuit to foreclose upon the liened property within six (6) months of the last day providing equipment, labor, materials or services for a project.

Recording a KY Statement of Mechanic’s Liens in Johnson County

A national manufacturer and installer of retail mall and storefront signs asked our TRADITION LIEN SERVICE division to record a KENTUCKY Statement of Mechanics Lien on a shopping center located in Paintsville, KY within Johnson County. According to Wikipedia, Johnson County was formed in 1843 and named for Richard Mentor Johnson, War of 1812 general, United States Representative, Senator, and Vice President of the United States.

General/Prime Contractors and Subcontractors on private Commercial projects can record a KENTUCKY Statement Of Mechanic’s Lien up to six (6) months after the last day providing equipment, labor, materials or services for a project. Record at the County Clerks Office where a project was located. Cost to record a lien with the Johnson County Clerk is $46 for up to five (5) pages. The office does accept out of state business checks. Make the check out to JOHNSON COUNTY CLERK. Include a self addressed stamped envelope.

Turn around time to record is same day received. Recorded liens and releases will be returned with one week.

Once a KENTUCKY Mechanic’s Lien is recorded, as Claimant you are required to file suit to foreclose within twelve (12) months from the date the lien was recorded.

Recording a TX Lien Affidavit in Hays County

An Austin, TX commercial roofing subcontractor that specializes in TPO (Thermoplastic Polyolefin is a single-ply roofing membrane used to cover flat roofs) asked our TRADITION LIEN SERVICE division to record a TEXAS Lien Affidavit (Subcontractor/Supplier) on a new self storage location in Dripping Springs, TX within Hays County. According to Wikipedia, Hays County is named for John Coffee Hays, a Texas Ranger and Mexican–American War officer.

On private Commercial projects TEXAS Property Code mandates that a General/Prime contractors and Subcontractors may file a notarized TEXAS Lien Affidavit for a commercial project by the 15th day of the month, four (4) months after the completion of providing equipment, labor, materials or services for a project. Record the lien with the clerk of the county in which the project is located. Cost to record a lien with the Hays County Clerk’s Office is $26 for the first page and $4 for each additional page. The office does accept out of state business checks. Make the check out to HAYS COUNTY CLERK. Include a self addressed stamped envelope.

Turn around time to record is 1-2 business days. Recorded liens and releases will be returned with one week.

Once a Lien Affidavit is recorded, lien claimants must file suit to foreclose on the lien within two (2) years from date a lien was recorded or one (1) year from entire project completion date, whichever is later.