Lien Deadlines And Notices
DISCLAIMER: TRADITION SOFTWARE, INC. makes no warrant, express or implied for the use of this website. In no event shall TRADITION SOFTWARE, INC. be liable to anyone for any problem, claim or loss arising out of the use of TraditionSoftware.com. TRADITION SOFTWARE, INC. is not engaged in practicing law in the state of Nevada nor does TRADITION SOFTWARE, INC. provide legal advice in the state of Nevada.
1ST Notice | NEVADA | Nevada lien law video
Commercial Existing Residential New Residential
Notice Of Right To Lien Notice Of Right To Lien Notice Of Right To Lien
NEVADA Revised Statutes § 108-245 mandates that on private Commercial projects Subcontractors have up to thirty-one (31) days to deliver by certified mail or personal delivery a NEVADA Notice Of Right To Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $26. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

NEVADA Revised Statutes § 108-245 mandates that on private Existing Residential projects Subcontractors have up to thirty-one (31) days to deliver by certified mail or personal delivery a NEVADA Notice Of Right To Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $26. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

NEVADA Revised Statutes § 108-245 mandates that on private New Residential projects Subcontractors have up to thirty-one (31) days to deliver by certified mail or personal delivery a NEVADA Notice Of Right To Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $26. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

Lien Warning | NEVADA | Nevada lien law video
Commercial Existing Residential New Residential
Notice Of Intent To File A Bond Claim, Notice Of Lien Or Stop Notice Notice Of Intent To Lien Notice Of Intent To Lien
Optional. Use a Notice Of Intent To File A Bond Claim, Notice Of Lien Or Stop Notice to notify all legal parties (Owner, Lender, Customer, Lender/Surety) for a Private Project that a Bond Claim, Notice Of Lien or Stop Notice will be filed if payment is not received by a stated deadline, usually ten (10) days.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $50. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects NEVADA Revised Statutes § 108-226 mandates that a NEVADA Notice Of Intent To Lien must be served to all legal parties (Customer, Owner, General Contractor, Lender) on a fifteen (15) days prior to filing a NEVADA Notice Of Lien with the County Recorders Office in the County where the project occurred.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $59. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects NEVADA Revised Statutes § 108-226 mandates that a NEVADA Notice Of Intent To Lien must be served to all legal parties (Customer, Owner, General Contractor, Lender) on a fifteen (15) days prior to filing a NEVADA Notice Of Lien with the County Recorders Office in the County where the project occurred.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $59. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

Construction Lien | NEVADA | Nevada lien law video
Commercial Existing Residential New Residential
Notice Of Lien Notice Of Lien Notice Of Lien
On private Commercial projects NEVADA Revised Statutes § 108-226 mandate that General/Prime Contractors and Subcontractors can record a notarized NEVADA Notice Of Lien up to ninety (90) days after the last day providing equipment, labor, materials or services for a project.

If a NEVADA Notice Of Completion was filed General/Prime Contractors and Subcontractors must record a notarized NEVADA Notice Of Lien within forty (40) days of the NEVADA Notice Of Completion being recorded.

Claimants are required to file suit to foreclose on a NEVADA Notice Of Lien within six (6) months from the date the NEVADA Notice Of Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $170. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects NEVADA Revised Statutes § 108-226 mandate that General/Prime Contractors and Subcontractors can record a notarized NEVADA Notice Of Lien up to nintey (90) days after the last day providing equipment, labor, materials or services for a project.

If a NEVADA Notice Of Completion was filed General/Prime Contractors and Subcontractors must record a notarized NEVADA Notice Of Lien within forty (40) days of the NEVADA Notice Of Completion being recorded.

Claimants are required to file suit to foreclose on a NEVADA Notice Of Lien within six (6) months from the date the NEVADA Notice Of Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $170. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects NEVADA Revised Statutes § 108-226 mandate that General/Prime Contractors and Subcontractors can record a notarized NEVADA Notice Of Lien up to nintey (90) days after the last day providing equipment, labor, materials or services for a project.

If a NEVADA Notice Of Completion was filed General/Prime Contractors and Subcontractors must record a notarized NEVADA Notice Of Lien within forty (40) days of the NEVADA Notice Of Completion being recorded.

Claimants are required to file suit to foreclose on a NEVADA Notice Of Lien within six (6) months from the date the NEVADA Notice Of Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $170. Or, you can print this NEVADA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.
 

Counties to record or release a NEVADA Notice Of Lien: Carson City, Churchill, Clark, Douglas, Elko, Esmeralda, Eureka, Humboldt, Lander, Lincoln, Lyon, Mineral, Nye, Pershing, Storey, Washoe, White Pine

For addresses of county recorder’s offices to mail or record in person a NEVADA Notice Of Lien, click here.