Lien Deadlines And Notices | ||
DISCLAIMER: TRADITION SOFTWARE, INC. makes no warrant, express or implied for the use of this website. In no event shall TRADITION SOFTWARE, INC. be liable to anyone for any problem, claim or loss arising out of the use of TraditionSoftware.com. TRADITION SOFTWARE, INC. is not engaged in practicing law in the state of Arizona nor does TRADITION SOFTWARE, INC. provide legal advice in the state of Arizona. | ||
1ST NOTICE | Arizona | ||
Commercial | Existing Residential | New Residential |
Twenty Day Preliminary Notice | Twenty Day Preliminary Notice | Twenty Day Preliminary Notice |
ARIZONA Revised Statutes § 33-992-01 mandate that Subcontractors have up to twenty (20) days to deliver by first class mail or personal delivery a ARIZONA Preliminary Twenty Day Notice to the Owner and all legal parties on a private Commercial project after first furnishing equipment, materials, labor or services. Each day after the 20th day, you lose 1/20 of your financial interest in the financial value of construction related labor, services, equipment or materials your company provided for the project. As an alternative, a Preliminary Notice may be given out at a later point in time, but your financial recovery for a Mechanic’s Lien, if filed, can only be for the twenty (20) day period prior to the Preliminary Notice being filed. TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | Subcontractors on Owner occupied Existing Residential projects must get a contract with the homeowner PRIOR to first furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite in order to have future lien rights. If a contract is obtained, ARIZONA Revised Statutes § 33-992-01 mandates that a Twenty Day Preliminary Notice (Private Work) must be delivered by first class mail or personal delivery to all legal parties on a project (Customer, Owner, General Contractor, Lender) within twenty (20) days after first furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite. Each day after the 20th day, you lose 1/20 of your financial interest in the financial value of construction related labor, services, equipment or materials your company provided for the project. As an alternative, a Preliminary Notice may be given out at a later point in time, but your financial recovery for a Mechanic’s Lien, if filed, can only be for the twenty (20) day period prior to the Preliminary Notice being filed. TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | ARIZONA Revised Statutes § 33-992-01 mandate that Subcontractors have up to twenty (20) days to deliver by first class mail or personal delivery a ARIZONA Preliminary Twenty Day Notice to the Owner and all legal parties on a private New Residential project after first furnishing equipment, materials, labor or services. Each day after the 20th day, you lose 1/20 of your financial interest in the financial value of construction related labor, services, equipment or materials your company provided for the project. As an alternative, a Preliminary Notice may be given out at a later point in time, but your financial recovery for a Mechanic’s Lien, if filed, can only be for the twenty (20) day period prior to the Preliminary Notice being filed. TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. |
|
||
LIEN WARNING | Arizona | ||
Commercial | Existing Residential | New Residential |
Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice | Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice | Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice |
Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien. TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien. TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien. TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. |
|
||
CONSTRUCTION LIEN | Arizona | ||
Commercial | Existing Residential | New Residential |
Notice Of Claim Of Mechanic’s And Materialman’s Lien | Notice Of Claim Of Mechanic’s And Materialman’s Lien | Notice Of Claim Of Mechanic’s And Materialman’s Lien |
ARIZONA Revised Statutes § 33-993(A) mandates that General/Prime Contractors and Subcontractors must record a notarized ARIZONA Notice Of Claim Of Mechanic’s And Materialman’s Lien with a copy (subcontractors only) of the previously delivered ARIZONA Twenty Day Preliminary Notice at the county recorder’s office in the County where the project occurred. The lien must be recorded within sixty (60) days after a Notice of Completion is filed, or one hundred twenty (120) days after the last day providing equipment, labor, materials or services. It should also be served by First Class mail or personal delivery to all legal parties on a project (Customer, Owner, General Contractor, Lender). As Claimant you are required to file suit to foreclose on the lien within six (6) months from the date the ARIZONA Mechanic’s Lien was recorded. You can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | ARIZONA Revised Statutes § 33-993(A) mandates that General/Prime Contractors and Subcontractors must record a notarized ARIZONA Notice Of Claim Of Mechanic’s And Materialman’s Lien with a copy (subcontractors only) of the previously delivered ARIZONA Twenty Day Preliminary Notice at the county recorder’s office in the County where the project occurred. The lien must be recorded within sixty (60) days after a Notice of Completion is filed, or one hundred twenty (120) days after the last day providing equipment, labor, materials or services. It should also be served by First Class mail or personal delivery to all legal parties on a project (Customer, Owner, General Contractor, Lender). As Claimant you are required to file suit to foreclose on the lien within six (6) months from the date the ARIZONA Mechanic’s Lien was recorded. You can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. | ARIZONA Revised Statutes § 33-993(A) mandates that General/Prime Contractors and Subcontractors must record a notarized ARIZONA Notice Of Claim Of Mechanic’s And Materialman’s Lien with a copy (subcontractors only) of the previously delivered ARIZONA Twenty Day Preliminary Notice at the county recorder’s office in the County where the project occurred. The lien must be recorded within sixty (60) days after a Notice of Completion is filed, or one hundred twenty (120) days after the last day providing equipment, labor, materials or services. It should also be served by First Class mail or personal delivery to all legal parties on a project (Customer, Owner, General Contractor, Lender). As Claimant you are required to file suit to foreclose on the lien within six (6) months from the date the ARIZONA Mechanic’s Lien was recorded. You can print this ARIZONA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159. |
|