WEST VIRGINIA

Lien Deadlines And Notices
 
1st Notice
Commercial Existing Residential New Residential
Preliminary Notice Preliminary Notice Preliminary Notice
 

Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private Commercial project is effective in reminding all parties of future Bond, Mechanic’s Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private Existing Residential project is effective in reminding all parties of future Bond, Mechanic’s Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private New Residential project is effective in reminding all parties of future Bond, Mechanic’s Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.


 
Lien Warning

Commercial

Existing Residential

New Residential

Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice

Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice

Notice Of Intent To File A Bond Claim, Mechanic’s Lien Or Stop Notice

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Mechanic’s Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.


 
Lien

Commercial

Existing Residential

New Residential

Notice Of Mechanic’s Lien – Laborer / Notice Of Mechanic’s Lien – Materialman / Notice Of Mechanic’s Lien – Subcontractor

Notice Of Mechanic’s Lien – Laborer / Notice Of Mechanic’s Lien – Materialman / Notice Of Mechanic’s Lien – Subcontractor

Notice Of Mechanic’s Lien – Laborer / Notice Of Mechanic’s Lien – Materialman / Notice Of Mechanic’s Lien – Subcontractor

On private Commercial projects WEST VIRGINIA § Code 28-2-13 law mandates that a WEST VIRGINIA Notice Of Mechanic’s Lien – Laborer be filed within one hundred (100) days after completion of a contract for a project.

WEST VIRGINIA § Code 28-2-11 law mandates that a Materialman’s Notice Of Mechanic’s Lien be filed within one hundred (100) days of last providing equipment or materials for a project.

WEST VIRGINIA § Code 28-2-9 law mandates that a Subcontractor’s Notice Of Mechanic’s Lien be filed within one hundred (100) days after completion of a Subcontract for a project.

The lien must be filed with the Office Of the Clerk of the county commission in the county where the project is located. A recorded copy should be promptly delivered by certified mail or personal service to the Owner and other legal parties (Lender, Owner Agent).

WEST VIRGINIA § Code 38-2-24 mandates the Subcontractor’s Notice Of Mechanic’s Lien must then be enforced through a foreclosure action within six (6) months of filing the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private Existing Residential projects WEST VIRGINIA § Code 28-2-13 law mandates that a WEST VIRGINIA Notice Of Mechanic’s Lien – Laborer be filed within one hundred (100) days after completion of a contract for a project.

WEST VIRGINIA § Code 28-2-11 law mandates that a Materialman’s Notice Of Mechanic’s Lien be filed within one hundred (100) days of last providing equipment or materials for a project.

WEST VIRGINIA § Code 28-2-9 law mandates that a Subcontractor’s Notice Of Mechanic’s Lien be filed within one hundred (100) days after completion of a Subcontract for a project.

The lien must be filed with the Office Of the Clerk of the county commission in the county where the project is located. A recorded copy should be promptly delivered by certified mail or personal service to the Owner and other legal parties (Lender, Owner Agent).

WEST VIRGINIA § Code 38-2-24 mandates the Subcontractor’s Notice Of Mechanic’s Lien must then be enforced through a foreclosure action within six (6) months of filing the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private New Residential projects WEST VIRGINIA § Code 28-2-13 law mandates that a WEST VIRGINIA Notice Of Mechanic’s Lien – Laborer be filed within one hundred (100) days after completion of a contract for a project.

WEST VIRGINIA § Code 28-2-11 law mandates that a Materialman’s Notice Of Mechanic’s Lien be filed within one hundred (100) days of last providing equipment or materials for a project.

WEST VIRGINIA § Code 28-2-9 law mandates that a Subcontractor’s Notice Of Mechanic’s Lien be filed within one hundred (100) days after completion of a Subcontract for a project.

The lien must be filed with the Office Of the Clerk of the county commission in the county where the project is located. A recorded copy should be promptly delivered by certified mail or personal service to the Owner and other legal parties (Lender, Owner Agent).

WEST VIRGINIA § Code 38-2-24 mandates the Subcontractor’s Notice Of Mechanic’s Lien must then be enforced through a foreclosure action within six (6) months of filing the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this WEST VIRGINIA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.