SOUTH DAKOTA

<
Lien Deadlines And Notices
 
1st Notice
Commercial Existing Residential New Residential
Notice Of Project Commencement / Notice Of Furnishing Labor Or Materials / Preliminary Notice Notice Of Project Commencement / Notice Of Furnishing Labor Or Materials / Preliminary Notice Notice Of Project Commencement / Notice Of Furnishing Labor Or Materials / Preliminary Notice
 
On private Commercial projects SOUTH DAKOTA Codified Laws § 44-9-50 mandate that General/Prime Contractors can record a SOUTH DAKOTA Notice Of Project Commencement to protect themselves and the project from liens filed by Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors.

If a General/Prime Contractor records a SOUTH DAKOTA Notice Of Project Commencement, SOUTH DAKOTA Codified Laws § 44-9-53 mandates that Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors must deliver by certified mail to the Owner and General/Prime Contractor a SOUTH DAKOTA Notice Of Furnishing Labor Or Materials no later than sixty (60) days from the last date providing equipment, labor, materials or services for the project.

Subcontractors have the optional to deliver a Preliminary Notice to the Owner and other legal parties soon after the start of a project. It is effective in reminding all parties of future Bond, Lien Statement or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private Existing Residential projects SOUTH DAKOTA Codified Laws § 44-9-50 mandate that General/Prime Contractors can record a SOUTH DAKOTA Notice Of Project Commencement to protect themselves and the project from liens filed by Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors.

If a General/Prime Contractor records a SOUTH DAKOTA Notice Of Project Commencement, SOUTH DAKOTA Codified Laws § 44-9-53 mandates that Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors must deliver by certified mail to the Owner and General/Prime Contractor a SOUTH DAKOTA Notice Of Furnishing Labor Or Materials no later than sixty (60) days from the last date providing equipment, labor, materials or services for the project.

Subcontractors have the optional to deliver a Preliminary Notice to the Owner and other legal parties soon after the start of a project. It is effective in reminding all parties of future Bond, Lien Statement or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private New Residential projects SOUTH DAKOTA Codified Laws § 44-9-50 mandate that General/Prime Contractors can record a SOUTH DAKOTA Notice Of Project Commencement to protect themselves and the project from liens filed by Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors.

If a General/Prime Contractor records a SOUTH DAKOTA Notice Of Project Commencement, SOUTH DAKOTA Codified Laws § 44-9-53 mandates that Subcontractors, Sub-subcontractors and subcontractors supplying materials to other Subcontractors must deliver by certified mail to the Owner and General/Prime Contractor a SOUTH DAKOTA Notice Of Furnishing Labor Or Materials no later than sixty (60) days from the last date providing equipment, labor, materials or services for the project.

Subcontractors have the optional to deliver a Preliminary Notice to the Owner and other legal parties soon after the start of a project. It is effective in reminding all parties of future Bond, Lien Statement or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.


 
Lien Warning
Commercial Existing Residential New Residential
Notice Of Intent To File A Bond Claim, Lien Statement Or Stop Notice Notice Of Intent To File A Bond Claim, Lien Statement Or Stop Notice Notice Of Intent To File A Bond Claim, Lien Statement Or Stop Notice
 

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Lien Statement or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Lien Statement or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Lien Statement or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $40. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.


 
Construction Lien
Commercial Existing Residential New Residential
Lien Statement Lien Statement Lien Statement
On private Commercial projects SOUTH DAKOTA Codified Laws § 44-9-16 mandate that a notarized SOUTH DAKOTA Lien Statement be recorded by a General/Prime contractor or Subcontractor within one hundred twenty (120) days from the last date providing equipment, labor, materials or services for a project. Record the lien at the Register Of Deeds office in county where the project is located.

A lien forclosure action must be initiated against the Owner within six (6) years of the last date recorded on the lien. The Owner may file suit to shorten the force the foreclosure action timeframe to thirty (30) days from the date the lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private Existing Residential projects SOUTH DAKOTA Codified Laws § 44-9-16 mandate that a notarized SOUTH DAKOTA Lien Statement be recorded by a General/Prime contractor or Subcontractor within one hundred twenty (120) days from the last date providing equipment, labor, materials or services for a project. Record the lien at the Register Of Deeds office in county where the project is located.

A lien forclosure action must be initiated against the Owner within six (6) years of the last date recorded on the lien. The Owner may file suit to shorten the force the foreclosure action timeframe to thirty (30) days from the date the lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.

On private New Residential projects SOUTH DAKOTA Codified Laws § 44-9-16 mandate that a notarized SOUTH DAKOTA Lien Statement be recorded by a General/Prime contractor or Subcontractor within one hundred twenty (120) days from the last date providing equipment, labor, materials or services for a project. Record the lien at the Register Of Deeds office in county where the project is located.

A lien forclosure action must be initiated against the Owner within six (6) years of the last date recorded on the lien. The Owner may file suit to shorten the force the foreclosure action timeframe to thirty (30) days from the date the lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $160. Or, you can print this SOUTH DAKOTA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.