DISCLAIMER: TRADITION SOFTWARE, INC. makes no warrant, express or implied for the use of this website. In no event shall TRADITION SOFTWARE, INC. be liable to anyone for any problem, claim or loss arising out of the use of TraditionSoftware.com. TRADITION SOFTWARE, INC. is not engaged in practicing law in the state of New Hampshire nor does TRADITION SOFTWARE, INC. provide legal advice in the state of New Hampshire.
1st Notice | New Hampshire
Commercial Existing Residential New Residential
Preliminary Notice Preliminary Notice Preliminary Notice
Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private Commercial project is effective in reminding all parties of future Bond, Notice Of Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.

Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private Existing Residential project is effective in reminding all parties of future Bond, Notice Of Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.

Optional. A Preliminary Notice delivered to the Owner and other legal parties soon after the start of a private New Residential project is effective in reminding all parties of future Bond, Notice Of Lien or Stop Notice rights for slow/non payment.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $25. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.


Lien Warning | New Hampshire
Commercial Existing Residential New Residential
Notice Of Intention To Claim A Lien Notice Of Intention To Claim A Lien Notice Of Intention To Claim A Lien
NEW HAMPSHIRE Revised Statutes Annotated § 447:5-6 mandate that within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a private Commercial project Subcontractors must first send to the Owner and other legal parties a NEW HAMPSHIRE Notice Of Intention To Claim A Lien before recording and perfecting (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $45. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.

NEW HAMPSHIRE Revised Statutes Annotated § 447:5-6 mandate that within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a private Existing Residential project Subcontractors must first send to the Owner and other legal parties a NEW HAMPSHIRE Notice Of Intention To Claim A Lien before recording and perfecting (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $45. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.

NEW HAMPSHIRE Revised Statutes Annotated § 447:5-6 mandate that within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a private New Residential project Subcontractors must first send to the Owner and other legal parties a NEW HAMPSHIRE Notice Of Intention To Claim A Lien before recording and perfecting (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $45. Or, you can print this NEW HAMPSHIRE notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $159.


Construction Lien | New Hampshire
Commercial Existing Residential New Residential
Notice Of Lien Notice Of Lien Notice Of Lien
On private Commercial projects General/Prime Contractors and Subcontractors must record and perfect (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project. A licensed NEW HAMPSHIRE attorney is required for this, as it is a court required action at the court or Deed Registry in the County where your work of improvement occurred.

The foreclosure action on a NEW HAMPSHIRE Contractor’s Notice Of Lien occurs simultaneously with recording of the lien, making the deadline to foreclose one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project.

NEW HAMPSHIRE also allows Subcontractors to privately sue on a contract to recover money.

On private Existing Residential projects General/Prime Contractors and Subcontractors must record and perfect (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project. A licensed NEW HAMPSHIRE attorney is required for this, as it is a court required action at the court or Deed Registry in the County where your work of improvement occurred.

The foreclosure action on a NEW HAMPSHIRE Contractor’s Notice Of Lien occurs simultaneously with recording of the lien, making the deadline to foreclose one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project.

NEW HAMPSHIRE also allows Subcontractors to privately sue on a contract to recover money.

On private New Residential projects General/Prime Contractors and Subcontractors must record and perfect (foreclose upon) a NEW HAMPSHIRE Contractor’s Notice Of Lien within one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project. A licensed NEW HAMPSHIRE attorney is required for this, as it is a court required action at the court or Deed Registry in the County where your work of improvement occurred.

The foreclosure action on a NEW HAMPSHIRE Contractor’s Notice Of Lien occurs simultaneously with recording of the lien, making the deadline to foreclose one hundred twenty (120) days after the last day providing equipment, labor, materials or services for a project.

NEW HAMPSHIRE also allows Subcontractors to privately sue on a contract to recover money.